Monteath & Powys Logo
  NEWS > General News | New Projects >> Nikkinba, Tomago
 
Home
Personnel
Services
Clients.html
News
Jobs
Enquiries
Links
 
 
Click here to view
Company Flyers
Case Study: The Port Waratah Coal Service Kooragang Expansion

The Project

Bechtel Australia was the construction manager responsible for the installation and alignment of more than five (5) kilometres of coal conveyors at the PWCS Kooragang Expansion Stage 3 in Newcastle Australia.

Prefabricated conveyor sections were delivered to the site and erected onto concrete trestle supports. Individual conveyor idlers (rollers) are required to be surveyed into position both horizontally and vertically within a tolerance of plus or minus 2 millimetres to provide very accurate tracking of a high speed conveyor belt carrying 10,500 tonnes of coal per hour to the ship loader.

A similar horizontal and vertical alignment tolerance is required for the module mounted ship loader tripper rails over the length of travel along 3 contiguous berths of 350 meters each.

The Challenge
Project Survey Team Manager, Andrew Baker of Monteath & Powys Surveyors, was responsible for providing a safe access to enable this alignment survey and mechanical adjustment to proceed.

The Monteath & Powys Solution

Andrew Baker used the three-sided configuration of the conveyor assembly and its design function for providing longitudinal transport to provide a mobile work platform-tagged the “boat”.

The preliminary plan was the culmination of client liaison, measurements of typical sections and idler spacing. This plan was presented to the Bechtel Field Engineering Manager, Rob Payton and the Client Project Design Manager, Owen Scott. Our engineering professionals tested the theory behind this concept and Rob Payton did the engineering drawings.

Port Hunter Fire & Fabrication constructed the lightweight aluminium structure with central anchor point for harness connection, central pin locking to retain platform against central idlers and end point safety rails. Four-point lifting lugs enabled easy attachment to mobile crane hooks for lifting onto position on selected conveyor, and careful sizing of platform facilitated usage on the variety of PWCS conveyor profiles.

The Implementation

The platform was launched and field-tested. The operations have exceeded engineering design standards and workforce expectations. All safety locking, movement and control systems have proved to be successful.

As well as an operations triumph, this project was also a financial success story. Within the first 7 days of operations, the efficiency improvements covered the cost of fabrication and development. The benefits of simultaneous access for both survey alignment and mechanical adjustment from a safe mobile platform was the culmination of a high benchmark in professional team achievement.

Other Monteath & Powys Projects Nikkinba Ridge Development,  Tomago Aluminium Project
           © 2007 Monteath & Powys Pty Ltd. INTERNET POLICY | PRIVACY POLICY